Landing Park wall nearing completion; more sidewalks poured; bridge and Columbia Street closures

Posted
Activities planned for week of April 22 - 26:
  • Start installing bridge lamp posts
  • Finish Landing Park wall
  • Concrete pours for curbs, planter seating, and sidewalks
  • Landing Park Closed
  • Woodin Avenue Bridge Traffic Closure (Monday - Friday Morning)
  • Columbia St  (Into Downtown) Closure (Monday - Thursday)
 
Activities planned for week of April 2 - May 3
  • Continue bridge lamp posts
  • Bridge concrete repairs
  • Installing pavers in sidewalks
  • Irrigation and landscaping
  • HMA patching
  • Landing Park Closed
  • Woodin Avenue Bridge Traffic Closure (Monday - Friday Morning)
  • Columbia St  (Into Downtown) Closure (Monday - Thursday)
 
Activities planned for week of May 6 - 10:
  • Bridge concrete repairs
  • Irrigation and landscaping
  • Grinding old asphalt
  • Asphalt paving
  • Traffic signs
  • Woodin Avenue Bridge Traffic Closure (Monday - Friday Morning

During closures, all roads are open to pedestrains and bicyclists. For safety, bicyclists are asked to walk their bikes due to the limited space and compromised condition of the roadway.

 
All aspects of the project are expected to be completed before Memorial Day Weekend, the end of May.


Note: This look ahead reflects what the contractor currently anticipates. Weather and other circumstances can change construction crew activities, and therefore road and park access. Please visit the website for the most up-to-date information.