PUD’s proposed 2027 budget puts $188 million toward dams, grid upgrades and wildfire protection

Posted

WENATCHEE – Chelan PUD’s proposed 2027 budget includes $188 million in capital investment for dam modernization, electrical system improvements and wildfire protection, supported by a stronger revenue forecast from wholesale power sales.

Commissioners reviewed the proposal during a second public budget hearing Nov. 16. The board is scheduled to consider adopting the budget Dec. 7.

The proposed spending plan totals approximately $545 million, including debt payments. It forecasts $567 million in revenue and $169 million in net income, about $45 million above the adopted 2026 budget.

Mark Mullins, the PUD’s director of enterprise financial planning, risk and analytics, said the annual budget translates the utility’s long-term plans into projects and work that can move forward.

“So the annual budget is not the strategy itself, but it’s really the near-term authorization so we can execute on that plan,” Mullins said.

Rock Island Dam represents the largest portion of planned hydroelectric investment. Work includes modernization of generating units at Powerhouses 1 and 2, improvements to the drop gate structure and electrical system upgrades.

The PUD also plans to build substations to meet growing community needs, including Bavarian Substation in Leavenworth and Bridge Street and Castlerock substations in Wenatchee. Upgrades are planned at College Substation in Wenatchee and Leavenworth Substation.

Wildfire protection includes planning to rebuild an existing high-voltage transmission line between Peshastin and Coles Corner using steel structures. Design and a proposed contract are expected to come before commissioners in fall 2027, with construction planned for 2028.

The budget also supports continued fiber expansion.

Mullins said the capital proposal had decreased by about $2 million since the first budget hearing Nov. 2 because three projects were not ready for funding.

Projected revenue is approximately $89 million above the adopted 2026 budget. A major contributor is increased revenue from surplus hydropower contracts after the PUD replaced a portion of its Alcoa contract with three smaller market-based contracts lasting five, seven and 10 years.

Operating expenses, including depreciation and taxes, are projected at approximately $413 million, about $39 million above the 2026 budget. Drivers include monthly financial settlements associated with the Canadian Entitlement allocation under the Columbia River Treaty and work on the PUD’s enterprise business software system.

Commissioners also unanimously approved a five-year rate plan Nov. 16 establishing annual increases of 5% for electricity, 2.5% for water and 4% for wastewater beginning June 1, 2027. Annual wholesale telecommunications increases of 2.5% begin in 2028. Staff said the adjustments are intended to narrow the gap between customer revenue and direct operating costs while reducing reliance on uncertain energy market sales.

Commissioner Steve McKenna said he struggled with increasing rates while households face financial pressures, but supported the plan after considering the PUD’s responsibilities over its 50-year planning horizon.

Staff forecasts continued strong reserves and low debt, giving the utility flexibility to address unexpected costs and changing conditions. The 2027 forecast includes approximately $420 million in liquidity and $24 million in scheduled debt principal payments.

Mullins said all four of the PUD’s district financial measures are projected to remain comfortably within policy requirements over the five-year planning period.